GOLAR GIMI FLNG MODULE PROJECT

From December 31st 2021, PV Shipyard has received, stored and preserved 4 HRSG modules at our yard, Vung Tau City, Vietnam.

Last 7th-9th March 2022, after completing the SPMT lifting test, turning and mooring the barge to PV Shipyard’s jetty;

PV Shipyard’s project team has successfully launched 2 modules onto the transportation barge.

During the launching process, the spreader bars manufactured by PV Shipyard were effectively used to distribute the load to ensure balance and safety.

After that, PV Shipyard carried out the installation of sea fastening for 2 modules to ensure safety for transportation at sea.

On March 12th, 2022, the above 2 modules were transported to Keppel port in Singapore.

And on March 19th, 2022, 2 modules docked at Keppel port on schedule.

On April 11th, 2022, PV Shipyard continued to launch and transport the remaining 2 modules from PV Shipyard to Singapore.

Expected schedule arrival at their destination is April 18th, 2022.

PV Shipyard always maintain the best schedule to deliver products to customers in the fastest, safest and most efficient way.

We thank our customers for trusting to choose PV Shipyard and we wish the project success.